Two-car garage being converted to a permitted 420 sq ft accessory dwelling unit in El Cajon, CA

Garage Conversions · Fletcher Hills, El Cajon, CA

Garage Conversion to Permitted ADU — El Cajon

Final Cost$94,000
Timeline11 weeks
CompletedApr 2026
📋 CA Lic #945572🛡️ Licensed & Insured⭐ 5-Star Reviews📍 San Diego County

The Project

A Fletcher Hills homeowner wanted to convert a detached 420 sq ft two-car garage into a permitted ADU for adult-child housing. Existing slab was sound but undersized footings, no insulation, no plumbing, single 15-amp circuit. City of El Cajon required full plans and inspections.

Why this matters in El Cajon

Garage-to-ADU conversions are one of the most cost-effective ways to add a permitted rental unit in San Diego County, but they come with structural surprises that detached new builds don't have. Existing slabs are often undersized for a residential live load. Original wall framing may not be insulated and may not meet current shear-wall requirements. Single 15- or 20-amp circuits cannot support a modern living unit. A conversion that ignores these issues will fail plan check or worse — pass plan check and fail final inspection. Done correctly, conversions can come in 25–40% under the cost of a comparable detached ADU because the existing slab and roof structure are reused.

Scope of Work

  • Architectural drawings and energy (Title 24) compliance
  • City of El Cajon ADU conversion permit
  • Underpin existing footings to current code
  • Frame interior walls, install R-15 wall and R-30 ceiling insulation
  • Plumb new bathroom (toilet, shower, vanity) and kitchenette
  • New 60-amp subpanel from main, all LED, mini-split HVAC
  • LVP flooring, drywall, paint, exterior siding repair on garage door wall
  • Replace garage door opening with framed wall + new entry door + window
  • Final inspection and Certificate of Occupancy

How Subworkit Contracting Delivered

Subworkit Contracting reused the existing slab (after engineering review) and the existing roof structure to keep the cost under $100K — a key budget constraint for the homeowner. All trades performed in-house, with Bernard Eldib managing the City of El Cajon inspections directly.

Materials & Specifications

Specific brands, products, and engineering specs used on this project. We document materials so the homeowner has a complete record for warranty claims and future maintenance.

Foundation
Existing slab reused after engineering review; new underpinning at perimeter where existing footings were undersized
Framing
Interior partition framing, new shear walls per Title 24, replaced garage door opening with framed wall
Insulation
R-15 wall batts, R-30 ceiling batts
HVAC
Single-zone ductless mini-split, 1-ton, 18 SEER
Plumbing
Tied into existing main, new 3/4" copper supply, ABS DWV, on-demand electric water heater
Electrical
60A subpanel from main, all LED, hard-wired smoke + CO detectors
Finishes
LVP flooring, drywall, paint, full tile shower, quartz kitchenette counter

Project Timeline & Process

11 weeks from start to final inspection. Each phase below shows what happened on-site, when, and why — the same level of detail you'll get on your project status update.

  1. 1

    Plans + permit

    Weeks 1–4

    Architectural drawings, Title 24, structural review of existing slab + roof, City of El Cajon ADU conversion submittal.

  2. 2

    Demo + underpin

    Weeks 5–6

    Garage door removal, interior demo of finishes, perimeter underpinning where required.

  3. 3

    Framing + dry-in

    Week 7

    Interior partitions, new exterior wall where garage door was, windows + entry door, exterior siding repair.

  4. 4

    Rough trades

    Weeks 8–9

    Plumbing rough for bath + kitchenette. Electrical rough. HVAC. Mid-rough inspection. Insulation.

  5. 5

    Drywall + finish

    Week 10

    Drywall, paint, LVP flooring, cabinets, fixtures, tile.

  6. 6

    Final + C of O

    Week 11

    Final inspection, Certificate of Occupancy, walkthrough.

Outcome

Certificate of Occupancy issued 2026-04-08. Final cost: $94,000 — $1,000 under the $95,000 fixed bid. Adult child moved in two weeks after C of O.

Permits: City of El Cajon — ADU conversion permit, C of O issued 2026-04-08

Related services we offer

Most garage conversions projects in El Cajon touch one or more of the trades below. Subworkit Contracting handles them all in-house under a single CA Lic #945572.

Also serving nearby cities

This project was completed in El Cajon, but Subworkit Contracting takes garage conversions jobs throughout San Diego County, including:

La Mesa · Santee · Spring Valley · Lemon Grove

Ready to Start Your Project?

Subworkit Contracting (CA Lic #945572) delivers transparent pricing, fixed schedules, and in-house crews across San Diego County. Free estimates.

Call Now — Free Estimate